Hi all!

So it’s about time we had our own thread!
We are building Henley’s Palace Q1 at Riverstone in Doreen, on our 530m2 corner block


Our timeline:
Bought land (already titled) – Feb 2014
Initial deposit – Jan 2017
Final deposit – March 2017
Colours appointment – May 2017
Tender & Contracts – June 2017

Additions / Upgrades:
- Austin Façade with balcony, part render
- Kitchen luxury upgrade pack (40mm stone on the island bench, undermount sink, pot drawers)
- Double glazing to windows
- Internal wall insulation
- Colorbond roof
- Grand Alfresco
- Under stair storage with access from garage
- Manhole to garage
- Timber to the whole staircase
- Walk in robe fit out to master
- Double shower to ensuite
- Shower niches
- Add door to ensuite opening
- Add sliding door to ensuite toilet
- Upgrade internal doors to translucent glazed
- Upgrade alfresco sliding doors to larger size
- Refrigerated cooling
- Zoned heating
- Cupboards above fridge space
- Pull out bin drawer in island bench
- Additional cabinets under breakfast bar in island bench
- Butler’s pantry fit out with stone bench top and sink
- Laundry benchtop, cabinet and overhead cabinets
- Wash and wear paint
- Luxury electrical package
- Gas point to alfresco
- Additional external tap
- CCTV prewire package

Estate requirements:
- Brickwork above garage
- Corner treatment

Colours section upgrades:
- Cat 2 carpet
- Cat 3 underlay
- Cat 1b flooring
- Cat 2 tiles for bathrooms and powder rooms
- Cat 4 bricks


Will post some photos of plans and colours soon!

Sounds grand with the Austin facade, refrigerated cooling and double shower to ensuite. Look forward to following your build.

Following



Building with Perry homes: http://forum.homeone.com.au/viewtopic.php?t=84756
So it's been a few months and we have been very busy!
Tender and contracts are long signed and sorted, we applied for our loan and first home owner grant and everything is approved

Most excitingly ... we have site cut booked in for Tuesday!! Then underground power and drainage through the week and slab prep and pour the week after
cannot wait to get started!!

Will try to remember to post photos here ... but there will be plenty of photos on our instagram page: our.henley.palace.q1
Related
16/04/2024
1
Henley Homes

Building A New House

Hi, If you give a set of criteria as to what means 'good' to you, it'll give others prompts to respond. We considered Henley early on but there were two factors that…

8/11/2023
1
Our house was beautiful until Distinctive Homes destroyed ou

General Discussion

of course there are legal avenues. You've already mentioned it. Sue them. I find it odd that lawyers wouldnt be willing to take on the case, given CCT evidence and…

22/01/2024
36
Builder connecting our new toilet for his trades

Bathrooms and Laundry

"Losers" "humanity" "off time" "your" "top notch" "love symbol" Sounds like ponzo is done using other people's toilets