Browse Forums Building A New House Re: Hickinbotham Build Northern Adelaide 423Nov 07, 2017 10:26 pm Entilzha no idea but will find out down the track. hoping frame finished and windows on by the time i come out on the weekend Frame takes 2-3 days so frame should be done Windows was in a day after frame was sighned off by council. Hickies reported to council, tradies sended in their check list and then council checked the frame. You can keep an eye on coincil websit where you saw your plans on the frame info will. Ome up there Re: Hickinbotham Build Northern Adelaide 424Nov 08, 2017 8:20 am he was a concrete expert and seemed knowledgeable over all and had a discussion about some things to expect and the site etc. As to a PCI inspection i will do some more research first and consult with the guy monitoring my build if he is seeing issues that should be checked and go through that PDF PCI booklet and decide when its time. Re: Hickinbotham Build Northern Adelaide 425Nov 08, 2017 8:42 am Entilzha he was a concrete expert and seemed knowledgeable over all and had a discussion about some things to expect and the site etc. As to a PCI inspection i will do some more research first and consult with the guy monitoring my build if he is seeing issues that should be checked and go through that PDF PCI booklet and decide when its time. Yes we are thinking to do self check depending how rest go, but sice we stil had no communication in regards to email/call its higly likely we will get some one in to back us if its not attended to, and checkout other things too lie iside roof etc... but have been there a couple of times taking lots of photos sofar only the consern with tge widows/slide doors Re: Hickinbotham Build Northern Adelaide 426Nov 08, 2017 9:10 am which they will rectify and surprised you haven't heard back yet considering will do a final review at the end on product review and will comment on all aspects of the process from start to finish Re: Hickinbotham Build Northern Adelaide 427Nov 08, 2017 9:16 am Entilzha which they will rectify and surprised you haven't heard back yet considering will do a final review at the end on product review and will comment on all aspects of the process from start to finish Yes Same, no idea whats going on with the call back, eve reception and colleagues have taken messages for her.. (unless she ison leave or off sick) But the final review wi included this parts communication. Its hard coming from guy with great communication to this he spoiled us and now we expect the same standard Re: Hickinbotham Build Northern Adelaide 430Nov 08, 2017 10:48 am I doubt that would be the case. probably just busy or absent - good luck with it Council site has now updated with the roof truss as designed amendment showing correct trusses and floorplan. But wont be able to get it checked by friend till early next week i expect but he did tell me some of the things he will be looking at last night just got sent the following picture by someone going past my block Hopefully that is enough roof for the 23 Solar Panels i want to put up Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Re: Hickinbotham Build Northern Adelaide 437Nov 09, 2017 7:41 pm Building wrapped. Windows in place.
Roofing booked for tuesday and lining tentatively booked in for the 29th. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Re: Hickinbotham Build Northern Adelaide 438Nov 09, 2017 8:10 pm Wow! Your running through your build! Our linings is booked for 15th (Wednesday) i send another email this morning and still no reply... funny i had a question for our selections consultant about our tangehood and 2 hours later she replied.... so guessing our aircon and electrical has to be done before the linings? Friends had their ducts for aircon and electrical done on monday past but still no linings ir delivery of them Hi, I'll be starting on my verandah repair soon - replace ledger, rafters, roofing iron, flashing etc. (fascia board already done). My question is about the timber ledger… 0 3334 1 2992 Hi All, see above image. The required setback from the rear boundary in my case is 5m, as you can see the shape of the site and location of the boundary is slightly… 0 8463 |