We're planning for our first build - so zero experience whatsoever in this. Appreciate all your inputs if you could please.
We have a lot with approximately 250mm fall. Builders that I contacted said it's good and within 'building criteria'.
Now, one of the builders' inclusion brochure, it says
"All site and specifications taken care of for you: building allotment of up to 650 square metres. “M” Class waffle pod slab. Connection to standard sewer and storm water connection points within the building allotment. Includes Part A Termite treatment. A maximum of 300mm fall over building area, a maximum of 12lm of underground single phase power and a maximum setback of 5m to house. Excludes rock removal, telephone service and consumer account opening fees."
But they quoted fixed site costs of $15,000 on top of their advertised building price for a particular design. My understanding is it's already covered by the inclusion, except for the rocks part.. Am i missing something? What would the $15k possibly for? A little bit lost..