Excavation completed | Apr 10, 18 |
Piering | Apr 13, 18 |
Setting slab forn board | May 2, 18 |
Slab pour completed | May 4, 18 |
Houspect slab inspection | May 8, 18 |
External drainage completed | May 16, 18 |
Stormwater Council inspection | May 31, 18 |
First floor frame up | May 28, 18 |
First floor frame finished/ Storm cert issued | Jun 4, 18 |
Plumbing rough in | Jun 14, 18 |
Roof frame up | Jun 14, 18 |
Ground floor brick laying commenced | Jun 4, 18 |
Housepect frame inspection | Jun 28, 18 |
First floor brick completed | Jul 3, 18 |
2nd Floor brick commenced | Jul 27, 18 |
Roof tile | Aug 11, 18 |
Top eaves, downpipes and rendering | Aug 13, 18 |
Façade completed | Aug 13, 18 |
scaffolding removed | Aug 16, 18 |
Tiles delivered | Aug 17, 18 |
Lower roof , cladding, gutter completed | Aug 23, 18 |
Electrical. Plumbing rough in | Sep 4, 18 |
Gyprock completed | Sep 19, 18 |
Stair installation completed | Sep 26, 18 |