Timeline So Far
- Land Purchase: 3/03/2017
- Settlement: 03/04/2017
- Design Selection: 01/07/2017 - Adenbrook Homes Ballina Austin Option B
- Initial Quote: 31/07/2017
- Premilinary Agreement Signed: 01/08/2017
- Soil and Contour Tests: 18/08/2017
- Tender Received: 16/09/2017
- Tender Accepted: 20/09/2017
- Next Stage Deposit: 20/09/2017
- Colour Room and Electrical Appointment: 29/09/2017
- Contract: 15/10/2017
- Finance: 26/10/2017
- 5% Deposit Paid: 10/11/2017
- Submitted to Council: 13/11/2017
- Council Approval: 23/02/2018
- Certified Approval: 08/03/2018
- Bank Commencement Notice Served: 12/03/2018
- Start Date: 09/04/2018
- Drains In: 15/05/2018
- Spoil Removal: 16/05/2018
- Slab Down: 22/05/2018
- Frames Started: 23/05/2016
- Frames Finished: 31/05/2016
- Gutters and Fascia: 03/06/2016
- Roof On: 06/06/2016