Browse Forums Building A New House Re: Architecturally Designed Home - Vic 61Jun 08, 2018 1:59 pm Builder managed to get a nice high shot from the cherry picker. steel is all in and finally taking form. garage brickwork is all done (not sure i explained that we had to knockdown everything as we wanted to widen the garage opening). but the brickies have a done a great job replicating what it looked like before. less pics in the next 4 weeks as all that's going to happen is the timber framing, then 4 more weeks of brickwork. but at least things are going up! Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Architecturally Designed Home - Vic 62Jun 09, 2018 6:26 pm Those curves are going to look amazing! Can't wait to see the brickwork. I love Art Deco lines, just a little jealous... Re: Architecturally Designed Home - Vic 63Jun 09, 2018 7:49 pm thanks! we can't wait till we are able to share some more advanced progress photos but i guess patience is the key here will post some framing photos every few weeks, but unfortunately there won't be much worth sharing for a bit Re: Architecturally Designed Home - Vic 65Jun 10, 2018 10:04 pm StructuralBIMGuy frankily thanks! we can't wait till we are able to share some more advanced progress photos but i guess patience is the key here will post some framing photos every few weeks, but unfortunately there won't be much worth sharing for a bit Yep, Patience is the Key along with Data & Proofs, Nice photo but you could have used a drone instead of a cherry picker thanks, i didn't take the photo, they had the cherry picker incidentally for the steel. i also don't have a drone unfortunately. Re: Architecturally Designed Home - Vic 66Jun 23, 2018 8:28 pm quick update the build is slowly progressing well. we've just finished the garage roof, framing is well underway with 90% of the wall frames done, will move onto the roof soon. brickies resuming next week to start where possible, other areas will need to wait for the windows to arrive. very exciting to be able to walk around the house including upstairs! Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Re: Architecturally Designed Home - Vic 67Jul 11, 2018 8:33 pm just a quick update, been too lazy to post photos basically external framing is all done, roof is going up in the next couple of weeks. we've started bricking where we can but most of it is waiting for the windows to come in 3 weeks. framing taking a bit longer as the curved roof, curved ceiling, plywood ceiling require a lot more complex preparation. aiming to finish bricks and get to lock up by end of August. looking forward to sharing some nice external photos Re: Architecturally Designed Home - Vic 69Jul 26, 2018 9:50 am ok. so we've finally finished framing! the below photos show the additional timber baton/grids that had to be installed. but we are there! Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ flat part of the roof is also up, the curved will be on Monday. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ timber frames coming next week and we've recommenced external brickwork. looking for lockup by end of August looking forward to posting more once it's done! Re: Architecturally Designed Home - Vic 70Sep 21, 2018 3:01 pm hi all long time between posts. been waiting for the scaffolds to come down, which happened today to share our exterior. brickworks all done, concrete floor has been grinded. plywood ceiling going up. we love the progress and very happy with the results Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ the curved brickwork just looks fantastic, the soldier bricks helps add depth, once the canopy goes up it'll help break up the facade bit more. unfortunately we do need to screen off the windows, which will happen in a couple of weeks Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ those sliding doors are 3.5m high, looks awesome from the inside and with some good curtains it'll be just as we pictured. top floor will be screened off as well. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ we are currently doing our curved plywood ceiling, which is bit complicated as it is comprised of 3 layers. can't wait till it's all done! Re: Architecturally Designed Home - Vic 71Sep 23, 2018 8:13 pm I'm guessing you are getting lime wash on the plywood ceiling? If you do it is going to look stunning.. Curve ceilings are such a great feature, can't believe time has flown so fast. Re: Architecturally Designed Home - Vic 74Oct 16, 2018 2:26 pm going well thank you! the ceiling is taking a while as the curved section is far more complex than anticipated. but overall still tracking well. finished the timber floors, starting plasterboards this week and tracking to finish by end of the year! got a mate to do some drone shots but the overshadow from tree was annoying. will share more once the boards are up Re: Architecturally Designed Home - Vic 75Nov 03, 2018 7:48 pm Quick update We've basically finished up the ceilings, which took ages, we had to leave the arched hallway until later so we can do the plasterboarding. plaster boards all done, most of the doors are hung, same with pergola and deck framing: Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ oops. missed photos November is going to be full of painting and wet areas with December for all the remaining fit outs. hoping to get handover just before Christmas! very excited Re: Architecturally Designed Home - Vic 76Dec 13, 2018 12:46 pm Hi all quick update The house is almost complete! it'll be 99% done by next friday, which is the builder's last day, unfortunately it is probably best if we didn't occupy straight away and give the builder's a week to go through final defects and everything else. So the final handover is going to be 18/1/19!! so excited, the house is looking great. We will get the keys next friday so we can start moving things in so i will do a full walkthrough video then, linked a short video just for now: https://vimeo.com/306099571 I have posted this before: We hired Darbecca to do every stage inspection, and I strongly recommend them to anyone that asks me. They were amazing. Thorough reports… 2 4495 We already paid for somfy motors for the blinds. The quote above was purely for “pre-wiring” so the blinds company can install the motors and blinds. That’s why we… 5 16268 From what I know about water tanks (I've been working with a client on them for a few years now) is this - The concrete can last a lifetime if they don't crack for some… 2 10629 |