Browse Forums Building A New House Re: Willaston by Statesman Homes SA 21Feb 28, 2017 1:21 pm So as mentioned above, I have been very slack in my updates...but next week is our walkthrough! So after months of delays due to terrible weather last year, we have pretty much completed our build and will be doing our walkthrough within 4 months. Below is an updated timeline. I will post photos this week. Timeline of Build: 18/7/16 Released to construction 28/10/16 Block levelled and compacted 3/11/16 Footings dug and soil removed 4/11/16 Plumbing and pipes paid 6/11/16 Plastic laid 7/11/16 Steel and mesh laid 8/11/16 Slabbed 18/11/16 Bricks delivered 21/11/16 Timber and framing delivered 24/11/16 Windows being delivered 24/11/16 Framing started 25/11/16 Framing and trusses finished 29/11/16 Plumbing started, gutters delivered 30/11/16 Gutters and fascias done. Skip delivered 1/12/16 Scaffolding for roof installed 5/12/16 Roofing installed 6/12/16 Brickwor stared and first fix electrical commenced 7/12/16 First fix electrical complete 9/12/16 Insulation installed and gyprock delivered 12/12/16 Gyprocking started, ceiling completed 13/12/16 Walls lined - gyprock done. Skirting and cornices delivered 14/12/16 Internal window framing started 15/12/16 First flush of gyprock 19/12/16 Second fix carpentry stated - all internal and external doors hung 20/12/16 Door frames started and skirting begun 4/1/17 Brickie continuing, carpenter has returned to continue skirting and door frames 5/1/17 Cornice work started 6/1/17 Bricking finished 10/1/17 Bath delivered and installed 12/1/17 Eaves completed 13/1/17 Cabinetry delivered 17/1/17 All cabinetry installed. Kitchen, bathrooms, pantry and robes. Waterproofing started in wet areas. Tiles delivered 18/1/17 Flyscreens installed 19/1/17 Downpipes installed 23/1/17 Painting started. First coat of ceilings done 24/1/17 Painting continues, walls and front door 30/1/17 Blinds and flooring both measured up 31/1/17 Tiling started 6/2/17 Second fix electrical commenced 11/2/17 Tiling completed 14/2/17 Roller doors installed 27/2/17 Toilets, sinks and taps installed Re: Willaston by Statesman Homes SA 22Mar 08, 2017 8:29 pm Congratulations, glad to hear it's all moving along. I'm looking forward to seeing pictures. Best of luck with the walk through. Ask for references and speak to them. If they are defensive or try to avoid the request, walk. 1 74546 I would never build with Fowler homes. I built with them in 2021 and till date maintenance issues are pending. All their existing trades and businesses don't work with… 14 105134 Hi there! Putting the feelers out there for those who have (or almost) built with Arli homes! Interested in your experiences who've built from their stock home designs… 0 23202 |