Browse Forums Building A New House Re: Building Henley Palace Lux Q1 5BR with MODs in West MEL 228Mar 03, 2019 7:27 am immu999 Hi Spice Girl, Hope your build is now completed and you've moved in? Our land was titled on 9th Jan and settlement was on 23rd Jan. There were some delays in submitting the application for Property Information to the council - Carlisle said they need this information to proceed with other things. Do you know what other things are required to be in place for admin work. My developer is very lazy and aparently they missed to apply my property information to council - three week delay already, they applied it today after i followed up. We had handover 21/12/18 and officially moved mid Jan. I'm not sure what else is required as building permit was quite quick. We did delay start once they started ordering and found some things were discontinued or our front door didnt meet Bush fire regulations or they came back with options to upgrade hot water system when supplier queried them. How's progress now for you? Hi All It has been a few weeks since my last update. The build has been progressing well. No major issues to report. The scaffolding was dropped today, gyprock will be… 96 356960 Hi I live in a 100yr old semi and my neighbour added an additional floor last yr and our architect has advised that we can knock down our semi and build a free-standing… 0 37714 It might be a bit darker in the mornings but the light is still light, so you should be getting it. Similar to what you see from your western windows 3 19987 |