My partner and i are building with Smart Homes for living, a modified version of "the colossus" on a 508sqm block in Byford!

We have our pre start on the 14/2/18 after many many months of organising our land, floor plans and contracts!
My first question: is there anything you’ve realised after your build of after you have signed contracts that you feel would of been a great idea to include: ie power point in a certain area ect.
2nd: for anyone who went through key start how long was the turnaround from submitting your formal application for finance until receiving notification all has been approved?
And 3: what was the rough turnaround of finance approval to slab down?
Cant wait to share more of our build once it gets started!

our timeline so far:
sept: pre approval
21/Oct offer on block!
24/Oct offer accepted
2/11 land deposit paid
6/12 final house plans received and signed
12/12 building deposit paid
28/01 land contract extended by 30 days
30/01 build quote signed
14/02 pre start!!!
23/02 final building contracts received and signed
1/03 FHOG and keystart application finally submitted!
14/3 building permit received
17/3 noticed a watertap on the block!
21/3 land contract extended by 30 days
23/03 FHOG approved
29/03 finance with keystart declined (cannot re apply until July)
30/4 land contract extended to 15 August.
17/07 re apply keystart
28/8 FHOG + finance approved, finally!
19/9 Settlement!
4/10 site works started
8/10 visited and noticed plumbing/ready for slab to be poured