Hi everyone,
After months of following all of your builds I finally decided it was time to create my own account and start a thread!
My partner and I have a block on hold in the Whistling Grove estate in Wandi.
Last night we signed our Pre Contract Quote with Home Group WA and are having our Building Contract fast tracked - should be signing next week to make the deadline for our block! I will post our house plan on Monday once it is sent through to us.
Please feel free to share any advise and suggestions you all have along the way and I hope you enjoy following our journey as I have enjoyed following yours
Thanks
Jess
Jan 16 - Began looking at land
29/1/16 - Put a block on hold in Wandi
11/3/16 - Signed for the block (subject to finance)
21/3/16 - Deposit paid on land
21/5/16 - First meeting with HGWA
01/6/16 - Deposit paid to HGWA
11/6/16 - Building contracts signed
22/6/16 - Formal finance approval
30/6/16 - Block settlement
17/8/16 - Tile & Laminate meeting
05/9/16 - Prestart completed
29/9/16 - Final documents signed and returned
13/10/16 - Building permit received
01/11/16 - Earthworks
09/11/16 - SLABBED!
21/11/16 - Bricks & frames delivered
28/11/16 - Brickwork started
08/12/16 - Roof timber delivered
09/12/16 - Roof carpentry
15/12/16 - Gutters & downpipes
16/12/16 - Electrical & plumbing tube
20/12/16 - Colorbond
11/01/17 - Grey float
16/01/17 - Ceilings & cornices
24/01/17 - Plaster
31/01/17 - Lock up external doors & windows
31/01/17 - Internal doors and shelving
06/02/17 - Cabinets
08/02/17 - Bath
11/02/17 - Tiling Began
20/02/17 - Tiling Completed
11/03/17 - Electrical & plumbing completion
16/03/17 - Garage door & HWU installed
22/03/17 - Paving completed & site clean
05/04/17 - Home Group's requested date for PCI
10/05/17 - PCI booked date, due to work commitments