Browse Forums Building A New House Re: Marriott Waters Site Costs Shock 4Aug 02, 2008 8:09 pm Hi there,
I posted recently about our "extravagant" site costs as well. For us, however, I cannot see why they would be so high, ie it is a small flat block with no sewerage pipe issues (and ours came in at closer to $40,000!!!! although $17,000 of this was a "provisional allowance" only. Still... ). My husband has ties to the building industry and when he asked a colleague (a builder with another company) about these charges he laughed and suggested they were trying to rip us off. Most people who replied to my post also agreed that the fees seemed over the top. I would strongly suggest you get another quote with another builder and see how they compare. I am still waiting for an estimation of costs from my husband's colleague to see how ours compares. Don't necessarily give up on the idea of building...just check to see that you are not being taken for a ride. Re: Marriott Waters Site Costs Shock 5Aug 02, 2008 9:54 pm kkaz Hi there, I posted recently about our "extravagant" site costs as well. For us, however, I cannot see why they would be so high, ie it is a small flat block with no sewerage pipe issues (and ours came in at closer to $40,000!!!! although $17,000 of this was a "provisional allowance" only. Still... ). My husband has ties to the building industry and when he asked a colleague (a builder with another company) about these charges he laughed and suggested they were trying to rip us off. Most people who replied to my post also agreed that the fees seemed over the top. I would strongly suggest you get another quote with another builder and see how they compare. I am still waiting for an estimation of costs from my husband's colleague to see how ours compares. Don't necessarily give up on the idea of building...just check to see that you are not being taken for a ride. Thanks - I have spoke to a couple of people in the business as well as civil engineer and they reckon it looks like the builder is "arse covering" Even though there may be some substance to the site costs we will have to go the trouble and expense and get a second opinion just to keep them honest Its the nature of the beast but should we really have to carry out all this due diligence- shouldn't there be checks and balances in the industry to protect the customer. We are at a disadvantage as the builder has the knowledge and tends to exploit their position . Good luck with your situation Re: Marriott Waters Site Costs Shock 6Aug 06, 2008 11:42 am bugger
we have a 2.5m sewer easement right down RHS of our block but we are fortuntet in that the block is big enough so we do not encroach on it. Our site costs for the house we were going to build came back at $8k which was really good we had thought. And that was upgrading to Class M from their normal S slab. Best of luck. Re: Marriott Waters Site Costs Shock 7Aug 06, 2008 3:09 pm Can I just ask a quick question here?
Are these $8K quotes fixed? ie is there no chance they will change after the contract is signed or DA is put through? The reason I ask is that I suggested to the company who quoted such high site costs that they were well and truly over=priced. She then suggested they were quite accurate, that all companies would charge that much (but might not be so up-front about them). SHe said a lot of companies will give a low quote, then hit the buyer with extra fees after the contract is signed or DA is through and it is more difficult to pull out of. SHe suggested using her fee structure when I went along to get another tender and to ask specifically about those "additional" costs to ensure they would not "pop up" later. The fact that she suggested this makes me think she might be telling at least a half-truth Has anyone actually got past the contract stage / DA stage, perhaps has already built their house, and found their site costs were still low?? Re: Marriott Waters Site Costs Shock 8Aug 10, 2008 2:24 pm HI All,
Just an update on the original quote we had from our builder on site costs at Marriot Waters Stage 3 The original quote was was $21,600 They have now reduced this by $4,000 - advising they are prepared to do it at cost as a gesture of goodwill. So our Fixed Price site costs will be $17,600 - this is without doing a soil test. We thought this was a decent reduction on the original price and are now about to sign the contract. Our only concern is signing up and paying the deposit now when settlement on Stage 3 is Oct and the build wont start until late Jan. Re: Marriott Waters Site Costs Shock 9Aug 10, 2008 6:10 pm How much is the deposit?
We are in a similar position - titles registered Sept and hopefully starting in Oct/Nov. We signed our Tender and had to pay a total of $3000. That locks in our price. We haven't signed our contract yet to pay 10% deposit - builder was happy holding off on doing this until titles are formally registered. After 4 years - we're in! Re: Marriott Waters Site Costs Shock 10Aug 10, 2008 6:44 pm stonecutter1309 How much is the deposit? We are in a similar position - titles registered Sept and hopefully starting in Oct/Nov. We signed our Tender and had to pay a total of $3000. That locks in our price. We haven't signed our contract yet to pay 10% deposit - builder was happy holding off on doing this until titles are formally registered. We already paid $1,000 to lock in our price until Jan 09. When we sign the contract we will have to pay PD the deposit - $10,800 We're thinking maybe wait until Oct before signing as we have the price held until Jan 09 anyway.The builder is expecting us to sign this week. Is anyone building with Mojo and have a recent site cost tender 0 16022 Henley should give you some indication of site costs. Too many variable to give you any reasonable accuracy 1 1903 Looking to tile the facade pillars rather than rendering. Builder is quoting 2500$ laying cost for upto 10msq. The 2 pillars come to be 16msq. So laying costs are 5000$… 0 7759 |