Browse Forums Building A New House 1 May 03, 2016 3:37 pm Hi we are near completion of our build but things arent moving as quickly as they once were. Driveway is down and house almost complete apart from a few small touchups here and there. Just curious to know how long handover was from when the gas metre was installed? Thanks Re: Gas metre 3May 05, 2016 8:06 am A few weeks or a month maybe? I can't remember if our gas meter went in before Christmas or after (handover on 25th of Jan, one PCI on the 18th of Dec and another on the 6th of Jan and the gas meter went in before one of those two PCI dates). We built the Rathdowne with Simonds Express in Western Melbourne Site start Oct. 2015 Keys Jan. 25th, 2015 My build thread -here- 4 10821 I want to build a decking to the drawn shape outlined in black. The problem is how close can I build to the gas hot water unit? Will I be able to build around it and be… 0 20224 you need a fridgie to answer but I would think you vac the whole system then add gas if you have a leak, unless it is new install with the gas already loaded, in that case… 1 3655 |