Thought id start my own thread of my journey building with Oracle. Its our first time building. Our timeline so far:
We sold our home March 2015
Have been renting since
Land was registered Sept 2015
Contracts signed with Oracle October 2015
Color selections made Nov 2015
DA approved in council December 2015
Construction certificate received March 2016
Estimated to go to site by end of this month (March)
Site cut 1st April
Plumbing 5th April
Framework for slab and pier holes 7th and 8th April
Frames 17th May
Gutters and fascia 20th May
House wrapped in sarking 23rd May
Roof bats and tiles place 24th May
Bricks started 10th June
Plumbing rough ins 23rd June
Electrical rough ins 27th June
Eaves June 27th
Front door hung and laundry and external garage door 27th June
Insulation 1st July
Gyprock 6th July
Eaves completed in front peak of facade and internal garage door hung 21/7/16
Plasterer set gyprock Fri 22nd July
Interal doors, architraves, cornices 1st august 2016
Cabintery delivered and kitchen installed 3rd Aug bathroom cupboards wrong color
Tilers started 12th Aug 2016