Journey so far.
Saw the land Sept 2015, Offer accepted.
Owner of the land Nov 2015
Re Financed on our own house at the same time.
Build Loan approval March 2015 ( after a lot of hic ups, re Broker!) Note to self, go straight to the bank next time.
Plans drawn up, (haven't seen them as yet) in the post this week.
Prestart booked for 16/3.
I'm trying to upload our plans. Umm another challenge
Hope to hear when process starts next week at Prestart.
Off to see Shane later at southport. Need to have another look around with a cuppa:)
Looking forward to seeing your plan!
Pre start tomorrow!:)
Variations paid for, we completed that back in March, added in another toilet for the bathroom, (named semi ensuite) we have added a door from the bedroom next door. Should add in we have made that side of the house wider by another metre. Our thoughts are, when our Son and his mates our there, they will use his bathroom and leave my nice fluffy girlie powder room alone!. Here's hoping anyway.
First progress payment paid today. The block has been levelled, so here we go......
Still trying to upload photos, not having muc luck. Top tips please.
Thanks for the read. Have a great day
Sort of getting the hang of it now