Hi guys
We are about to start building our new house which of course means we have our DA and CC. It's over 3 levels - garage excavated into the ground then rumpus then topped off by our main upper level.
We are about to start and complete the garage level and the slab for the rumpus level - BUT... we suspect that we aren't going to be able to build the upper level (as approved) due to the cost. We are starting to consider our alternatives.
This is what has been suggested: Start building as per plan. If funds do run out Section 96 a change to my upper levels which will be similar in shape but less expensive to build. Has anybody, or know of anybody, who has done this and can this be done? (If I do need to change it would be REALLY good as there will be ALOT less excavation involved)
Would like to hear any advice!
Jayne