If this is done in time handover will be this Saturday but otherwise it will be next week/weekend!!
Building Metricon Glendale 42 Limited Edition in Geelong
Page 130 of 138
If this is done in time handover will be this Saturday but otherwise it will be next week/weekend!!
We are on track for PCI re inspection Wednesday morning, only issue that won't be finished is the stair stain. They have found the source of problem, painters got Old Baltic paint but some reducer wasn't put in it to tone down the colour or something, he said like full strength cordial. Soooo they have to sand back a bit and re stain. We've asked them to go darker because we are worried they would have to sand it too far to get ALL colour out and they might botch it up!! so asking for black Japan, just have to wait for confirmation.
If this is done in time handover will be this Saturday but otherwise it will be next week/weekend!!
If this is done in time handover will be this Saturday but otherwise it will be next week/weekend!!
Awesome Kylz best of luck Wednesday
That's not bad just staining to go I'll be crossing both fingers and toes for you.
Metricon Metro 32 KDRB Bayside Melbourne
http://forum.homeone.com.au/viewtopic.php?f=31&t=84012
Do you know the brand? Maybe you can google the instructions?
Oh good thinking!!!!
Black Japan or black??
I would go Black Japan as it still shows a bit more of the wood textures.
Same thinking here
Some pics from yesterday
Finally our side fence is finished
Rendered alfresco
And our moonshadow bricks that had colour washed off quite a bit after too strong acid wash have been fixed up. They have lost their different tones
Those bricks still look good after the tidy up they look a whole lot better than before.
The render looks good just a shame about the 'no care' attitude towards the surrounding areas.
I like the two tone of the fence.
They are going to stain darker and I've asked for door to be done also due to all our hassles! He's said he will speak to higher management about it but might be a possibility π€π€
Renderers still need to finish alfresco and front piers
Nawkaw might still need to come back re mortar colour to front bricks
Carpet has been stretched to meet tiles properly at ensuite and bathroom/toilet. Looks a lot better but can tell it's a tight fit as you can see between carpet fibres to white mesh a little where it folds down. They won't replace it so we want it in writing that if it wears there in short period they will replace it then
Stacker door to first floor is rattly
Quadding at front door looks a bit wonky, drops down to join corner.
Need inspector to check garage roofing thoroughly to see where leak may have been coming from as m haven't been able to find anything!
Related
13/12/2023
0
Hi, First of all, thank you to this community for sharing your thoughts and opinions. We are in early days of our pre-contract stage for Metricon Doulton and we are…
29/01/2024
0
Hello All π We are planning to start our journey of construction our first home. We zeroed down on Metricon and henley homes based on design suitable for our lot and…
15/03/2024
0
We donβt live in VIC so want to know the exterior colours of Lumiere display so we can see it at the paint shop. Not building with Metricon so my request went…