Hi all, I am building in Sydney and my builders's build time for double story house (around 39 squares) is 36 weeks. When I inquired why longer they said its because if there is delay for unavailability of tradies. However in contract liquidated damages are $1.00 per working day. Is it fair they have already considered delays to calculate the build time and still liquidated damages only $1.00 per day.
Thanks.