After reading this forum for a few months now we have used the wide variety of info to help us with our decision to build the new PD design Rowland 41.
After signing in mid May we have chosen colours, had our Tender and signed our contract with a guaranteed start in August.
After a few hiccups with some of the "creative" pricing we are generally happy with our choices.
We have now been told that they will start building at the end of July but they have added 75 extra days of building time due to the changes we have made (not that there have been many) and XMas. So we should be in around March.
BTW we are building in Melb Sth East. We will try to keep you updated with pictures as things unfold.
Cheers
GG.