I have used this forum a fair bit to see what other people have done, ideas and information about different builders and HomeGroup themselves.
Anyway, now I have signed up myself and making our own thread for our new house that we will be building.
We have signed up with HomeGroup WA to build their Lancaster complete home.
We have modified the standard floor in a few places:
- We have added an additional garage and a manual roller door to the rear
- Completely modified the kitchen layout to be the same or very similar to the platinum display home including a servery window to the alfresco
- modified the ensuite to be a similar style to the platinum display home too.
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Some perspective views
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
We are buying a 544m² block in butler, the old Brighton estate but in a private sale.
Settlement for that is in a few days on the 22nd
TIMELINE: (I'll update this as we go)
03/07/2015 - First made contact with HomeGroup WA
15/09/2015 - First plans drawn
22/09/2015 - Site works estimating
09/11/2015 - prestart
08/12/2015 - tap installed on site
12/12/2015 - handed over signed final drawings
14/12/2015 - Building permit received
15/12/2015 - start of scheduling process
19/01/2015 - noticed electrics box installed on site
31/01/2016 - earthworks done
15/02/2016 - slab footings done
17/02/2017 - slab complete
02/03/2016 - bricks delivered
18/03/2016 - started brick laying
11/04/2016 - reached plate height, bricks done!
12/04/2016 - roof materials delivered around here
13/04/2016 - roof structure started
29/04/2016 - Electrical and pluming run in done
04/05/2016 - Steel roof done
06/05/2016 - Grey float started (render)
11/05/2016 - Grey float finished
13/05/2016 - Ceilings and Cornices installed
17/05/2016 - Front render done
18/05/2016 - Internal white set started
27/05/2016 - White set finished (just some touch ups to go)
31/05/2016 - Lock up!
31/05/2016 - Internal doors, WIR fit out and alfresco timber trim fitted
14/06/2016 - noticed cabinets installed in kitchen, laundry and scullery, bath also cemented in and tiles delivered
21/06/2016 - showers water proofed and nib bricks put in
21/06/2016 - front door varnished
22/06/2016 - Front render painted, internal ceilings painted, internal doors painted
22/06/2016 - Stone bench top install started
23/06/2016 - Tilers started, 2nd coat of paint on front render done
25/06/2016 - Grano (garage floor) done
01/07/2016 - Tilers finished (we are doing the main tiles after hand over)
05/07/2016 - Oven and range hood installed
07/07/2016 - Electrician finished, sliding robe doors installed
07/07/2016 - Gas hookup done
10/07/2016 - bathroom mirrors, toilets, rest of taps, shower screens installed
13/07/2016 - insulation put in, another coat of paint on doors
15/07/2016 - aircon installed
18/07/2016 - pavers delivered
21/07/2016 - driveway prepared for pavers, en suite bath fitted, hot water system fitted
25/07/2016 - Eave vents fitted
26/07/2016 - House clean
29/07/2016 - Flyscreens fitted
01/08/2016 - Paving started
02/08/2016 - Carpets started
03/08/2016 - Carpets finished, Garage doors fitted
30/08/2016 - PCI, final inspection
02/09/2016 - Got keys!