Well over due for starting a build thread but here goes.
What are we building:
Builder: Henley
Model: Vogue Q2
Facade: Cleo (Option 2)
Where are we building:
Suburb: Officer, VIC
Estate: Arcadia Estate (formerly Aspect)
Stage: 12
When are we building it:
Colours: 10/09/2015
Tender: 06/10/2015
Contract: 03/12/2015
Soil Test: 23/06/2016
Land Title: 30/06/2016
Construction Commenced: 25/08/2016
Construction progress/schedule:
Tempory Fencing: 25/08 - Done
Site Cut: 29/08 - Done
Set Out: 31/08 - Done
Underground Power: 01/09 - Done
Drains: 02/09 - Done
Slab Works: 06/09-12/09 - Done (took 3 days more than expected, mostly due to rain)
Pre Pour Inspection: 12/09 - Done
Slab Pour: 13/09 - Done
Framing: 30/09 - Done (took them less time than the 3 weeks they estimated )
Framing (and slab) inspection: 03/10 - Done
Lockup: ???
So far (touch wood) the process with Henley has been pretty smooth. It was the floor plan that really sold us on this home design. We love (almost) everything about it.