We found our block in October 2014 in Eliza ponds Coogee at 398sqm corner block we really wanted to still have a small yard as this is our forever home (better be!) we decided to go 2 storey. As from reading through most people's experiences we were super keen on 101 then had a rude unorganised rep when we sat down even after going through some of our points he showed us a standard plan. After doing the same with Ben Trag we walked in welcomed with open arms with a custom plan drawn off of there own to keep costs down. And a custom quote all binded up in a file. Needless to say decision made!
We started plans etc with Ben Trag around feb had contracts and pre start by May final plans and council approval by July and here we are now with our slab poured on sep 4th 2015. 12months to go! No complaints so far hopefully it stays like that!:) so here is afew snaps of what's happened so far!

OFFICIAL FINAL PLANS :
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
PRESTART SELECTIONS :
Outside colours identical to make decisions a bit quicker just copied the display of course including the 1200w 12340 with Omni handle how could we resist??

Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
TILING SELECTIONS :
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Kitchen
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Ensuite
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Bathroom
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
FLOORING SELECTIONS :
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
THE LADY VITO!
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
BASINS:
Matte white
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
TAPS:
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
INTERNAL DOORS:
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
BLOCK:
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
SLAB FOOTINGS:
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Hope you guys enjoy staying updated!:)
Slab sep 4th 2015
Bricks started mid sep 2015
Plate height mid October 2015
Trusses installed end October 2015
Upper slab pour nov 2015
Upper frame work Windows and eps clad mid/end Nov 2015
Fascias eaves gutters and render early dec 2015
XMAS BREAK RETURNED JAN 6TH
Colourbond delivered and installed early Jan 2016
Scaffold drop mid Jan 2016
Lower roof carpentry started and completed week 3 of Jan 2016
Elec/plumbing/fascias/gutters and eaves completed last week of Jan plus render sand delivered! Jan 2016
Waiting on colour bond delivery fingers crossed for lower roof this week!! Feb 2nd 2016
Grey float finished feb 8th
Feb 10th Colourbond delivered for lower roof
Feb 15th lower roof started
Feb 17th lower roof and flashings completed
Feb 18th plasterboard and cornices delivered
Feb 19th insulation installed and white set on walls
Feb 20th plasterboard install started
Feb 26th ceilings cornices and upper walls and rooms completed
Feb 28th meeting with supervisor before lock up
4th March stairs completed and little site clean.
8th March LOCK UP!


11th ceiling/cornice/ door painting
13th upstairs bath in
15th stair wall completed
20th waterproofing/screed in wet areas ready
20th internal painting started but wrong colour woops haha
21st external render colour nearly finished
25th GRANO POURED! some plumbing moved around so hopefully render colour can finish soon can't wait to see cabinets and garage door! Hurry up tile meeting I need to get in!!
29th March cabinets delivered and installed! Render complete!:)
April/may/June forgotten updated dates

Bench tops
Plumbing started
Electrical started
Tiling delivered stolen re delivered and finally laid haha
Shower screens and mirrors
Bath stolen
Hws and aircon done
Downpipes all done
Patching started for painter
Kryssti
Ben trager build 2015/2016