Browse Forums Building A New House Re: I normally Love Christmas but ....... 7Aug 20, 2015 7:21 pm My topic thread: viewtopic.php?f=31&t=76249&start=20#p1316378 Re: I normally Love Christmas but ....... 11Sep 23, 2015 8:17 am Gypsyhabitat Is the 14 weeks they have given you from site works to keys? That is so fast if it is! We are at about 10 weeks now and only up to grey float! about 1 year and 4 months in if you include the delays in titles and paperwork and scheduling lol It seems that various states build houses differently - over in Vic (and probably Tas?) I believe that most if not all of our internal walls are framed/stud walls with plasterboard over them, they aren't built with brick and then grey float/white float like they are in WA etc. As such it seems that some builds can be quicker than others, I guess it can depend on the builder and what they can do. We were going to go with Carlisle Homes and they offer a 20 week build guarantee. However, we are now going with a smaller builder who are saying 6 months (but won't guarantee that either).... My blog: tashandpaul.wordpress.com Not sure who you're building with, but I moved in recently to a 11month scheduled, 8 month actual build on the South coast/Illawarra NSW 3 5913 Joe, it depends on your certifier but we are noticing the ones we deal with are really cracking down. So i would recommend you follow your approved landscaping plans to… 4 10976 |