We are building for the first time in Calleya Estate, Banjup, WA. As per Stockland, our (Stage 26) title should be issued during September 2015.
We are preparing to sign a PPA with ContentLiving. Anybody building with them?
Thanks for your assistance and advise.
Our Building Diary:
01 Aug 2015: Preparation of Plan Agreement (PPA) Signed
04 Aug 2015: PPA Deposit Paid
05 Nov 2015: Land Settled
10 Feb 2016: Pre-Start
22 Mar 2016: Slab Down
08 Apr 2016: Bricks Delivered
13 Apr 2016: Brickwork Started
13 May 2016: Roof Finished
16 May 2016: Internal Rendering started
20 May 2016: Internal Rendering Finished
20 May 2016: Glass fitted
03 Jun 2016: Doors installed and Lockup
06 Sep 2016: 1st PCI
21 Sep 2016: 2nd PCI
03 Oct 2016: Keys Handover