I have decided to start my own post to share my progress,
This is a big step and have found everyone helpful on here
10/06/15 - Deposit on Block of land
15/07/15 - (Hopefully) Final Changes made to design,
7/11/2015 - Visited colour selection (goldcoast) to view what 'In range" included and have time to think about things and any upgrades
20/12/2015 - Signed our Pre title Contract
27/12/2015 - Signed our building Contract
-------- 2016 ---------
07/01/2016 - Vistied coral sale office to confirm things like telephone line (So on)
15/01 - 05/02 - Un replied emails.....
03/02/2016 - Went to Beaumont to select tiles (were told that they didn't have a job number yet)
06/02/2016 - New tender letter (due to changes not included Corals fault) - Didn't sign new tender letter as still had errors (spelling, Pricing, Designs, Still had water tank included)
- Assigned place for hot water, Gas, Fridge, Oven, Dish washer)
- Asked what was next was told we would have to wait for a new tender letter then wait 3 weeks for the plans to be drawn up then submit to council (8weeks)
So even tho our land will hopefully be registered in the next week or so we will be sitting empty handed.....