As the title suggests, we have decided to build the popular Glendale 38 Plantation design by Metricon on our newly registered block of land (450sqm) in Sydney's southwest. Our land registered in June 2015 so we are still awaiting for developer and council approval.
Here is a quick timeline of our progress so far-
Land purchase: June 2014
First deposit to Metricon: December 2014
Tender: February 2015
Contract/ external colour selections: March 2015
Land registers: June 2015
Land settled: 4 July 2015
Stockland approval: 24 July 2015
Plans submitted to council: 7 August 2015
Internal colour/ electrical appointment: 28 August 2015
Council approval: 12 October 2015
Final construction drawings received: 6 November 2015
File passed to construction: 11 November 2015
Site pegged- 17 November
Site cut- 18 November (official start date)
28 nov- piering
03 dec- drainage and formwork
04 dec- formwork and waffle pods/ steel works
08 dec- slab poured
15 dec- storm water drainage
18 dec- ground floor frames delivered
06 jan- ground floor frames commenced
11 jan- ground floor frames finished
14 jan- windows delivered
19 jan- First floor frames delivered
21 jan- first floor frames commenced
29 jan- first floor frames complete, windows installed
02 feb- bricks delivered
03 feb- first walk through
15 feb- bricking commenced
18 feb- plumbing
23 feb- scaffolding delivered
24 feb- scaffolding erected
29 feb- fascia/gutter delivered
02 mar- fascia/gutter installed
30 mar- bricks finished
7 apr- eaves installed
9 apr- first floor bricks cleaned
10 apr- upper gutters installed and painted
18 apr- render to front pillars
21 apr- roof tiles delivered
26 apr- sarking and tile battens installed
27 apr- roof tiles on
2 may- fascia and gutters to garage and rear rooms
3 may- painting/ stain to balcony gable
6 may- electrical rough ins
12 may- lower roof tiles/ cladding
17 may- insulation
18 may- pre lining inspection, plaster start
19 may- plaster finish
20 may- stairs installed
24 may- front door, internal doors, door jambs, skirtings and architraves
26 may- cornices
30 may- cabinetry delivered
31 may- waterproofing
1 june- rainwater tank/ cabinetry installed, painting commences
2 june- 2nd layer waterproof
15 june- benchtops, sinks and basins
We have not made much changes to the standard floor plan but here is a list of some of our upgrades:
- 450mm eaves to ground and first floor
- semi cantilevered staircase with glass balustrades
- 2550mm ceiling to ground floor
- convert powder room to bathroom
- butlers pantry
-square set and full wall tiling to all bathrooms and ensuite
-additional robe in master bedroom
-increase first floor linen cupboard
-added wash basin to first floor WC
Here is our floor plans as of 2 July 2015
Here is a visual of our facade
Bricks: Austral Whitsunday Orpheus
Roof tiles: Bristile Classic Coal
Gutters/ Windows/Downpipes: Monument
Fascia/ Render: Surfmist
Gables/ Timber posts/ Front door: Jarrah stain
Garage: Colorbond Caoba
This is our first ever build so any suggestions/ comments are very much welcomed