HI All, long time stalker, only a few posts under my belt
We are in the midst of 'shopping' for a builder and a final plan. My questions relate to the order of things. Is this right or how should it be?
Approach some builders who's designs we like, talk about changes to floorplans, inclusions, upgrades etc.
Hopefully receive some concept plans back and from those, make a decision on builder.
Pay a deposit and progress to detailed plans with as much included as possible.
Final contracts
Finance
Pre Start, which ideally you won't spend a lot at IF you've included everything at the detailed plans stage
Sign off
Earthworks
Construction
Lock Up
Handover
Is this right?
And should we be starting with the 'base' models of the plans we like and adding to them or go straight to the display range?