Hi everyone.
So we (wife and I) have just signed a contract with National Homes (yesterday) to formally begin our new house build. It has taken too long to get from the PWA to here, but now that we are I am hoping that things will move a bit quicker. The interaction we have had with the sales team (Theo and Brian) has been excellent so I would recommend them in a second. Just need to get BGC Residential to operate at their level, and I am sure we will.
We are building in Bicton WA, on an old block with a small house we will demolish to make way for the new.
We are very excited about this build and are really looking forward to seeing it unfold. And fortunately my work address is not far from the build site so hopefully I can swing by regularly to monitor progress, and report it here.
The all important TIMELINE follows:
30JUL2014 - Bought block in Bicton.
04AUG2014 - Deposit paid to National Homes.
06OCT2014 - Signed PWA with National Homes.
21FEB2015 - Signed Contract with National Homes.
03MAR2015 - Preliminary selections sent in.
15APR2015 - Pre-start meeting.
01MAY2015 - Pre-start selections all finalised.
18MAY2015 - Final drawings issued.
02JUN2015 - Old house demolished, site cleared.
09SEP2015 - Admin stage complete.
18SEP2015 - Siteworks STARTED !!!!
30SEP2015 - SLAB DOWN.
16OCT2015 - Bricks delivered.
03NOV2015 - Bricklaying started.
08DEC2015 - Roof Carpentry begun.
22FEB2016 - Lock Up.