Just wanting to share my journey with Ben Trager homes as there are not many reviews and i feel at the moment they have been fantastic for my partner and I.
Went display house viewing - 5th of October 2014
We initially wanted to go with 101 residential (we didn't even know Ben Trager existed). When we went into the house the sales rep was very rude. He judged us because we were young. After looking at the house we thought we would chat to him see his thoughts and as soon as the words keystart came out of our mouths he didn't want to know us. Pretty much said we wouldn't be able to build a double storey with them and sent us out the door. We then walked over to Ben Trager and never looked back.
Conditional Finance Approval - Keystart 15th of October 2014
Met with Jadon from Ben Trager - 19th of October 2014
Signed land Contracts with LWP - 8th of November 2014
Decided on final house plans and paid our deposit - 1st of December 2014
Contracts signed with Ben Trager - 24th of January 2015
Formal finance approval from Keystart - 11th of Feb 2015
Pre start booked in for - 27th of Feb 2015
Land titles due end of Feb
Land titles were given 12th of March 2015
Settlement Date 30th of March 2015
Final Plans received, signed and returned to BT - 28th of April 2015
File sent to Construction

Slab booked - First week of June
Re pegging 24th of May 2015
SLABBED!! 28th of May 2015
Bricks delivered 15th of June 2015
Brickwork commenced 23rd of June 2015
Brickwork complete 15th of July 2015
Roof beams delivered 18th of July 2015
Upper slab poured 19th of August 2015
Upper floor roof & wall framing complete 25th of August 2015
Roof complete 26th of August 2015
Upstairs render complete 15th of October 2015
Eaves and Gutters upstairs complete 22nd of October 2015
Scaffolding taken down 23rd of October 2015
Lower roof frame & Fascias complete 3rd of Nov 2015
Electrical's and Plumbing complete 19th of Nov 2015
Roof Sheeting delivered 19th of Nov 2015
Internal render complete 3rd Dec 2015
Internal insualtion complete 5th Dec 2015
Roof Complete 8th Dec 2015
Internal gyprock complete 8th Dec 2015
Cornacing Complete 9th Dec 2015
Door and window delivery 9th Dec 2015
Glass doors and windows installed 11th Dec 2015
White set complete 12th Dec 2015
Doors Hung 21st Dec 2015
Locked up 21st Dec 2015
Hobbs built, bath & laundry trough in 25th Jan 2016
Ceiling & upstairs painted 25th Jan 2016
Screed and waterproofing complete 23rd Jan 2016
Cabinetry carcasses installed 4th Feb 2016
Stone bench tops installed 11th Feb 2016
Tiling complete 18th Feb 2016
Garage grano complete 30th March 2016
All internal painting complete (door frames, front door etc) 30th March 2016
Bottom story eaves, facias and down pipes painted 30th March 2016
Oven, range hood and cooktop installed 30th March 2016
PCI2 - House finally complete 9th May 2016
If any one has any questions please feel free to ask.
Thank you for sharing this journey with me!