Hi Guys,
We have had land waiting to be titled since June 2013 and we have signed up with home group wa.
We have got our tile and laminate meeting in 2 weeks and then to prestart after this, does anyone have any recommendations or suggestions
We are building a modified version of the Mediterranean
BUILDING TIMELINE
27/3/15 - land titles issued
17/04/15 - settlement on land
01/05/15 - Prestart completed
05/06/15 - Final Documents finished and sent out
08/06/15 - Entered the scheduling department
15/06/15 - Final Docs signed off and variations put through
15/06/15 - building permit application sent to council
26/06/15 - building permit approved
17/06/15 - scheduling completed earth works estimated for the 24th July
24/07/15 - earthworks started! Woohoo!
27/07/15 - pipe work completed
28/07/15 - mesh and footings and reinforcing completed
29/07/15 - slab pour booked (no slab completed yet)
30/07/15 - slab down! Yippiee!
31/07/15 - soak wells delivered and invoice for slab received
05/08/15 - soak wells put in and site clean booked for 10/07
10/08/15 - site clean completed and yellow sand delivered for bricks
12/08/15 - bricks delivered, awaiting brick layer confirmation
17/08/15 - bricklayer started
20/08/15 - site meeting
24/09/15 - bricks finished plate height reached
25/09/15 - brickwork building inspector to site
26/09/15 - roof timbers delivered
02/10/15 - roof timbers finished and eaves completed
07/10/15 - pre plumbing and pre electrical completed
08/10/15 - colourbond delivered
09/10/15 - colourbond finished
15/10/15 - grey float completed
20/10/15 - ceilings finished
21/10/15 - cornices finished
02/10/15 - white set finished
03/10/15 - windows and sliding doors installed
04/11/15 - lock up complete
05/11/15 - ceilings and doors painted and wardrobes installed
11/11/15 - bath installed
12/11/15 - Cabinets installed, bench tops installed and first coat of render completed
17/11/15 - Grano down
19/11/15 - Tile meeting
21/11/15 - Tiling started
23/11/15 - Tiling of bathrooms finished
24/11/15 - Driveway prep and pavers delivered
25/11/15 - Toilets Delivered
30/11/15 - Render Completed
01/12/15 - Driveway Completed
09/12/15 - Aircon installed
16/12/15 - Final plumbing and electrical completed
17/12/15 - Garage door on and final painting completed
18/12/15 - House site clean completed
04/01/16 - Carpet Installed
05/01/16 - Flyscreens installed
13/01/16 - PCI Booked for 22nd Jan!
22/01/16 - PCI Completed with building inspector and SS
10/02/16 - KEYS!
15/02/16 - Tiling started
24/02/16 - Tiling Finished
24/02/16 - Bulkhead started
26/02/16 - Bulkhead Finished
29/02/16 - Electrician
02/03/16 - Painter
18/03/16 - Moved in!
30/03/16 - concrete
09/04/16 - planter boxes completed