Hi guys, after reading thread here, I am very eager to write up my own thread. We are about to weeks away from signing our final Contract with Atrium Home. This is my second home, well it is my and wife dream home. After running around with lots of builder we end up with Atrium home. I am waiting on the site quote so I know if I can include the ducted air con or not.
Time line
20/11/2013 decided to build a new house.
08/02/2014 Sign to buy a block of land.
10/03/2014 Finance approved subject to land tiles.
25/05/2014 Land tiles released.
20/06/2014 Settlement The block is our .
07/08/2014 Put our house on the market.
26/08/2014 House is sold.
26/09/2014 Say good bye to the house that I lived in for 20 years .
02/10/2014 Settlement for the house
11/10/2014 Sign agree with Atrium home
22/11/2014 Received fully document addenda
08/12/2014 First pre start – structure and modification changes
05/01/2015 Second pre start- colours, electrical layout etc.
09/02/2015 Contract Signed Yay!
27/02/2015 slab is done.
03/30/2015 Soak well installed
10/03/2015 window frames delivered, removal of excess sand.
To be continue
Here is my house final drawing of my house plans.
Ground floor
upper Floor
Elevations
looking into my block
looking out of my block