Wed site cut
Thursday sediment control
Friday fence up
Monday piering is booked in!
I may start a new thread as
1 i drive past the block everyday as we are renting down the road.
2. Im also a subbie involved in the build. Which is great as i have control of the tiling only.
Those interested in timeline we went to construction list 9 months and 1 week after tender.
From Construction list Mojo started exactly 20 working days after. Bit of delay with 3 shortened weeks. (Easter and anzac).
Good part is soil had some time to drain after all that march rain and less likely to get any settlement post construction of a water logged substrate!!
No bunched public holidays till xmas so qe should see some good productivity up to end of November.