Browse Forums Building A New House 1 Dec 30, 2014 12:02 pm Hi Everyone, We're building with Simonds Homes in Victoria. Received the Frame Stage invoice today and requires payment by 2/01/15. We provided frame stage inspection defects from my private inspector a couple of weeks back which have yet to be rectified. Just checked the contract again and it states stage is complete when approved by a building surveyor. Am I required to make payment now or only after they fix the defects raised by my private inspector? Thanks in advance. Hi, I am approaching end of the build. My final invoice will be given to me soon to pay. Some context before I ask my question. 1. My builder wont do the landscaping or… 0 3038 Hi All, I engaged a tradie to install concrete retaining wall 600-800mm high over 32 meters in Victoria. Sleepers are 200*75*2000 mm installed over 17 steel posts. I… 0 3710 1 7827 |