Didn't go too bad, mostly smaller issues like chips in walls, cracked or poorly done cornices etc.
Few other things that are a bit more obviously like the white set not done on the theater window yet which in turn needs the blinds put on (blind guy rocked up as the inspector was doing his thing), none of the vents have been flumed, the piping is there but not connected, cracked render outside and a few holes that need patching in the grouting between bricks and a bit of flashing down the side of the garage zero lot wall that hasn't been painted.
I'm sure there were a few other small things but nothing that the commissioner can't do in a day or so.
We're meant to have 10 working days until keys, so hoping to keep to that schedule. Supervisor said definitely in by Christmas but we've handed in our rental notice now and booking dates for deliveries so lets hope we're running on time!