I have been debating if I should start my own post to keep track of the whole building process. Yes, I did it like finally. YAY!!!
16.08.2014 - Secured the block. Title estimate to be released in Jan 2015.
03.10.2014 - Signed agreement with builder. Deposit paid.
13.10.2014 - Received final our final floor plan and addenda.
06.11.2014 - Tiles selection @ European Ceramics.
28.11.2014 - PRESTART.
17.12.2014 - Got an update from Providence admin that title will be released within the next 7 days.
05.01.2015 - Land settled
14.01.2015- Land contour surveyed
16.01.2015- Engineers site condition inspection
20.01.2015- Builder sent off for Developer Approvals
22.01.2015- Developer approved
26.01.2015- 6 star energy report & structural engineer report received. Builder applied for Builders license.
05.02.2015- Receive Building Permit!!! so fast! (Hopefully slab down soon)
13.02.2015- Slab Down
26.02.2015- Brickwork Started
10.03.2015- Brickwork Completed
11.03.2015- Roof Timber delivered to site
17.03.2015- Roof Carpenter starting on site
20.03.2015- Roof Carpenter completed
24.03.2015- Plumbing Tube in
25.03.2015- Electrical Tube in
30.03.2015- Roof Cover completed
01.04.2015- A/C Ducting
07.04.2015- Grey Float started
08.04.2015- Grey float finished
13.04.2015 - Plaster Set Completed
14.04.2015- Ceiling
17.04.2015- Window Glazing
20.04.2015- Door & Shelving delivered to site
21.04.2015- Lock up
23.04.2015- Painting garage ceiling, internal ceiling, eaves and doors
23.04.2015- Cabinetry /tiles delivered
24.04.2015- Laundry trough and bath were installed
________________________________________________
Counting down to PCI ..
Stone top install- DONE
Tiling- DONE
Floor Covering
Robes
Shower Screens
Mirrors
Garage concrete- DONE
Garage door - DONE
Appliances install - in progress
Final Painting -In progress
Final Electrical -DONE
Final Plumbing - DONE
A/C - DONe
Paving
Here's our floor plan.