Hello to all on H1 forum.
What a fantastic forum! Just finished reading many other building journeys and thought I'd start a record of ours.
We originally wanted to build in Corimbia, Landsdale but just couldn't find a block for the house we wanted. So ended up looking closer to DHs work and discovered Woburn Park!
What a lovely area with already beautifully established homes.......we managed to secure a 835sqm block.
Here is our journey so far
20/02/14.....Signed with Aveling Homes
01/04/14.....Contracts/drawings
14/05/14.....Prestart
23/05/14.....Land titled
30/05/14.....Settlement on land
30/07/14.....Received Building Permit (in only 7 days)
01/08/14.....GOING INTO CONSTRUCTION!
14/08/14.....Earthworks started
21/08/14.....SLAB!
30/08/14.....Drains etc completed
04/09/14.....Window frames, bricks & portaloo delivered
14/10/14.....Lintels, door frames, cement etc delivered
20/10/14.....Elec, front door frame, scaffold delivered
24/10/14.....Bricks started
05/11/14.....Bricks finished
17/11/14.....Roof started /gutter etc
02/12/14.....Roof tiles delivered
23/12/14.....Grey float int render started
12/01/15.....Roof ridge capping tiles cemented
12/01/15.....Internal grey float finished
02/02/15.....White set completed
07/02/15.....Ceilings installed