Hi,
I signed up with 101 Residential in late 2012. 101 Res. were promoting a 6 month build on television at the time (still are i think) and this was the only reason I signed with this company as the rent I am paying is quite high so obviously the quicker the build the better. The sales rep confirmed the 6 month promise. The plan was submitted to local council in February 2013 however was held up for almost 6 months by local council. In August 2013 we were given the all clear to go ahead and build. Of course it is now August 2014 and we are still approx. 4 months away from completion!!! I am now totally broke and the money I had put aside to manage the rent and draw down/mortgage payments is gone and life is one big struggle. Communication with MF is almost non existent and SP has not responded to text. Has anyone else out there had a similar experience?
MH