Browse Forums Building A New House 1 May 19, 2024 5:21 pm Hi, is anyone familiar the timing to inform builder, we are claiming for liquidated damages? We are currently at interior fit out stage and the builder has sent Extension Of Time (EOT) with the last letter mentioning the EOT is on 23rd May 2024. If anyone can advise their own experience and if they mail is suffice to builder or a proper letter attached to the email attention to the builder is a way to go? Thank you 🙏 It worked for me in getting all non notified rain days removed from the builders claim, although the LDs was only $50/day 7 6160 Thanks for your reply! We're definitely not after a small house Might still have a chat to them. Who did you end up building with if you don't mind me asking? 2 2734 I apologise for any confusion, but your understanding is correct. We approached our situation differently based on advice from… 11 54171 |