Browse Forums Building A New House Re: Building with Wisdom Homes 14374Mar 17, 2019 12:37 pm becks81 ASJ1981 Our ground floor frames and first floor frames (that was a tongue twister LOL!) were done last week! SS said in his weekly call last Friday that next week's tasks will be internal plumbing, termite guard installation and also bricks will be delivered next week. Really happy with his communication so far! We obviously couldnt get out of the car due to the rains and mud! So admiring from afar Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Such awesome progress, so happy for you. Things are moving fast! You'll be at lock-up in no time! Doesn't look small at all! Haha thanks becks81! It does seem like it's going fast. But I'm sure it will slow down towards the end - always the way! The first call from our SS was even before slab was done and he did say he had 7 weeks worth of jobs locked in and booked for our build. How's it all going on your end? Re: Building with Wisdom Homes 14375Mar 17, 2019 12:48 pm ASJ1981 becks81 ASJ1981 Our ground floor frames and first floor frames (that was a tongue twister LOL!) were done last week! SS said in his weekly call last Friday that next week's tasks will be internal plumbing, termite guard installation and also bricks will be delivered next week. Really happy with his communication so far! We obviously couldnt get out of the car due to the rains and mud! So admiring from afar Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Such awesome progress, so happy for you. Things are moving fast! You'll be at lock-up in no time! Doesn't look small at all! Haha thanks becks81! It does seem like it's going fast. But I'm sure it will slow down towards the end - always the way! The first call from our SS was even before slab was done and he did say he had 7 weeks worth of jobs locked in and booked for our build. How's it all going on your end? Wow so fast. My frames took 6 weeks because Christmas shutdown was in the middle Re: Building with Wisdom Homes 14376Mar 17, 2019 2:14 pm ASJ1981 becks81 ASJ1981 Our ground floor frames and first floor frames (that was a tongue twister LOL!) were done last week! SS said in his weekly call last Friday that next week's tasks will be internal plumbing, termite guard installation and also bricks will be delivered next week. Really happy with his communication so far! We obviously couldnt get out of the car due to the rains and mud! So admiring from afar Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Such awesome progress, so happy for you. Things are moving fast! You'll be at lock-up in no time! Doesn't look small at all! Haha thanks becks81! It does seem like it's going fast. But I'm sure it will slow down towards the end - always the way! The first call from our SS was even before slab was done and he did say he had 7 weeks worth of jobs locked in and booked for our build. How's it all going on your end? All the waffle pods and formwork is in situ and just waiting for the concrete to be poured next week, booked for Tuesday so fingers crossed. I know the frames have been ordered as they had an issue they needed to resolve urgently on Thursday. Manhattan52 are the bricks delivered and being laid yet??? Re: Building with Wisdom Homes 14377Mar 17, 2019 3:47 pm becks81 yes brick have been going for 5 weeks so far. It’s scheduled to finish this Thursday but weather may delay. Next week brick cure 4 days then brick wash then render on the front Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Re: Building with Wisdom Homes 14378Mar 17, 2019 7:27 pm Manhattan52 @becks81 yes brick have been going for 5 weeks so far. It’s scheduled to finish this Thursday but weather may delay. Next week brick cure 4 days then brick wash then render on the front Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Wow, this is massive. What size is your block? Re: Building with Wisdom Homes 14379Mar 17, 2019 7:30 pm Femstar Manhattan52 @becks81 yes brick have been going for 5 weeks so far. It’s scheduled to finish this Thursday but weather may delay. Next week brick cure 4 days then brick wash then render on the front Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Wow, this is massive. What size is your block? 2200m2 Re: Building with Wisdom Homes 14380Mar 17, 2019 8:15 pm Manhattan52 Femstar Manhattan52 @becks81 yes brick have been going for 5 weeks so far. It’s scheduled to finish this Thursday but weather may delay. Next week brick cure 4 days then brick wash then render on the front Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Wow, this is massive. What size is your block? 2200m2 Nice, that’s more than decent. Will be good to see how everything looks like after completion. Can someone please offer some advice? Im DESPERATE. Because I'm completely and utterly exhausted. How long are variations taking with other companies at the moment? We… 0 18470 In fairness nobody gave a crap about the ACCC and the gag clauses continued in the pro forma templates of a few other builders after the ACCC took on Wisdom, and more… 19 73488 Hi Everyone, I am exploring builder in NSW and received a very tempting quote from Wisdom home for their momentum series. I just want to know experience of building… 0 8240 |