Everything on site is looking good although I failed to get many interesting photos because I was too busy trying to document where all my wires were running! Our lower roof is in at the back, although we’re still missing the garage part of the lower roof.
Kitchen bulkheads have also gone in
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
And our stacker doors are in place...lockup is coming!
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
We had an inspector go through too and he picked up a few minor issues with straightening a wall, fixing a pipe and a couple of floor trusses that needed extra fixing to the frame. Pretty minor stuff.
Our SS sent over some update photos today to show the remediation work...so happy to see all that soundscreen insulation!
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Gyprock was due to start today, originally it was scheduled on Wednesday but it was bumped back a couple of days for the remediation work.
Building Wisdom Aspiration 31 at Willowdale
https://ourwillowdalehome.wordpress.com/
Our gyprock is done! They got it all done on Friday/Saturday last week so they could invoice us before EOFY we got the invoice on Saturday afternoon!
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Waiting for my weekly call today to find out what is next because I expected gyprock to be much slower than that so didn’t ask what is next!
Building Wisdom Aspiration 31 at Willowdale
https://ourwillowdalehome.wordpress.com/
We had stairs done next, that was a very exciting part of the build for me
Can’t wait to see your internals take shape
[/quote]
Yep SS confirmed this morning that stairs are booked next week along with waterproofing. Plasterers are on site this week to finish up all the internal walls and put up the cornices (coving? Showing my English side here...I can never remember which one is the Australian term!)
Building Wisdom Aspiration 31 at Willowdale
https://ourwillowdalehome.wordpress.com/