Sorry its been a while since i posted but just to give people a quick update our frames and roof trusses were all completed prior to the Christmas break and with tradies resuming last week we should have our ground floor brickwork completed by the end of the week. Then we are hoping its not too much of a wait until the first floor is completed and the roof laid but there is a shortage of bricklayers at the moment.
I had a quick question for those at PCI or Handover or beyond - what was the timeline from brickwork starting to Handover? We have to buy quite a bit in the way of furniture and appliances and want to take advantage of sales when they appear but we don't want to be storing things. I think we have late April/early May in our heads but am wondering if that's being overly optimistic.
Also for any of you based in Western Sydney - any landscapers or blind makers that you recommend?
Thanks
Hi Greg_K,
We moved in just before Christmas.
Our bricks were laid on 02-06-15 and we had handover on 11-12-15 for a Majestic 40 (double storey).
I have a timeline on my blog but I need to update it:
https://majestic40atgardenersridge.wordpress.com/our-construction-journey/