Hubby and I very excited to start our first build with Simonds Homes "Prague" with modifications to original floor plan. Our experience with Simonds has been really wonderful from the start. We went with their broker and He has gone above and beyond to get unconditional approval on time for land settlement.
Prague is originally a 19sq home but we have modified it to 22.5sq home. Adding extra room for a study or activity room with double doors and also added 3.7meters extention to meals area. It looks huge now like a big open plan. I haven't found anybody else who is building the Prague.
The plan is not clear and one side of the page
missing.
Big major mistake from my end was we didnt read the plans properly (even after going over it 1000 times) we missed it. The window across from the kitchen island is small, same size as in bathroom. We thought that it was the same size as the one in the meals area which is huge. Didnt realise until the frames was up.

So, I don't know why it saved like that.
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
This is the original floor plan
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
We love the plan as it fits on our small block.
And Here is our completed timeline.
07/02/14 paid deposit on land
05/03/14 gallery selections done
14/04/14 contracts with Simonds signed
24/04/14 unconditional approval granted
09/05/14 land settled
10/05/14 site started
21/05/14 base stage
28/05/14 Frame stage
30/05/14 Lock Up
07/07/14 Fixing stage
Awaiting Carpets and PCI
14/08/14 PCI completed
27/08/14 Handover... keys!!!