Browse Forums Building A New House Re: HIA Contract Period 48 weeks.. normal? 2May 16, 2014 9:42 pm What sort of house & what's involved? Ours is a knockdown-rebuild, our contract says 39 weeks but started with a cleared block (ie. the knockdown & clearing was before the 39 started). Christmas added another 3, rain has added another 2. Neither landscaping nor concreting (driveway) included. Ours is about mid-sized for a two-storey. Re: HIA Contract Period 48 weeks.. normal? 4May 16, 2014 10:11 pm How big is your house though? Blog http://tobuildahomeimprobable.blogspot.com.au/ Settlement Apr Council Jul Contracts Dec Earthworks Dec Frames Jan Trusses Feb Roof Feb Windows Mar Re: HIA Contract Period 48 weeks.. normal? 11May 22, 2014 10:41 pm Forg uncyspam Ours is 20 weeks for a 350m2 house! I think you might be getting screwed... Double this is normal, in Sydney, for a 350sqm house in Sydney by a project builder. Well done! I'm in Canberra, and building a custom. I believe that McDonald jones and rawsons both do 24 weeks for single story down here You talk about deletions, are they variations or PS and PC adjustments? pleas list them 1 16454 10 12208 Unless there is something in special conditions the builder does not have to give you timeline. If your demolition contractor has not removed Asbestos and it was found… 12 28684 |