Hi people,
I was reading many blogs here so I decided to make my one for the future hose. We are a young couple and we are in early stage just signed the PPA with Easystart. We where looking some land south of the river but not so far south and kind of low budget we don 't care much about having a big house, because we are just 2, but we I like gardening so we need some backyard space.
So we found a block 372 m2 in Lumen Rise (http://www.lumenrise.com.au/), Martin close to Gosnells. The builders (Easystart) contacted the land developer and the block is
Class S and has BAL 12.5 so they estimated 25K for site works and 8K for the BAL ... what do you think is OK???
Until now the money spent has been 1500 deposit for the house and we have to pay 3000 deposit for the land
I will be posting the progress in here
here is the plan of the house http://www.easystarthomes.com.au/home-f ... /the-genoa
Cheers and good luck in your own building projects
David and Kym
Updated--- Construction starting!!!!!
29/09/2015 – Water approval - tap installed
06/10/2015 – Building permit issued
06/10/2015 – Scheduling completed
15/10/2015 – Land Settlement
23/10/2015 – Siteworks completed
02/11/2015 - Footings completed
03/11/2015 - Slab completed
25/11/2015 - Bricks & window frames delivered
01/12/2015 - Bricklaying started
18/12/2015 - Bricklaying completed
4/01/2016 - Roof Carpenter completed
18/01/2016 - Electrical- GAs -Water tubes completed, External Render, gutters and tubes
20/01/2016 - Colorbond installed completed
2/02/2016 - Inside render, ceilings completed