Timelines:
HANDOVER has completed 20/1/2015
PCI has been completed 16/1/2015
FINALS has been completed 16/12/2014
LOCKUP AND FIXING has been completed 19/11/2014
PLASTER AND CEILING has been completed 03/11/2014
ROOF COVER has been completed 06/10/2014
BRICKLAYER has been completed 10/09/2014
CONCRETOR has been completed 11/08/2014
SITEWORKS has been completed 4/08/2014
SCHEDULING has been completed 25/07/2014
WATER APPROVAL has been completed 24/07/2014
BUILDING PERMIT has been completed 11/07/2014
MORTGAGE REGISTRATION has been completed 4/07/2014
FINANCE APPROVAL has been completed 4/07/2014
PRIVATE CERTIFIER has been completed 2/07/2014
FINAL PLANS AND DOCUMENTATION has been completed 26/06/2014
6 STAR APPROVAL has been completed 12/06/2014
ELECTRICITY has been completed 10/06/2014
GAS has been completed 10/06/2014
DRAFTING has been completed 9/06/2014
LAND SETTLEMENT has been completed 5/06/2014
DEVELOPERS APPROVAL has been completed 2/05/2014
ESTIMATING has been completed 1/05/2014
PRESTART MEETING has been completed 10/04/2014
PLANNING APPROVAL has been completed 24/03/2014
CONTRACT SIGNED has been completed 17/03/2014
I am building Minerva with New Generation Homes in Heron Park, Harrisdale, WA.
http://www.newgenerationhomes.com.au/ou ... he-minerva
Colors selected by us are:
1) Roof tiles: Astral
2) Feature wall: Roman brick Boston grey (same as of display home)
3) Garage Door and Hardiflex: Jarrah from Centurion (both same color)
4) Render: Possibly Surfmist Still confused
5) Entrance Door: Same color as that of Garage door
6) Paving: Granite Vistapave Tundra
Will appreciate for suggestions on design or color selection.
Cheers,
AB