Hi EmyN,
To be honest at the stage we are at we do not even have a handover date yet which has been a little disappointing. The build started 2 weeks before xmas and what needs to be done is plumbing fitoff, paint touch ups, mirrors, shower screens and splash back. I expect handover to be in the next 3 weeks but are having some supply issues with our toilets as the ones they installed were wrong. I was told 16 weeks which seems close to where we are now given the holiday shutdown.