First Build in Jane Brook with Home Group WA
Page 3 of 5
We were a little worried our neighbour had a similar house design but they don't - thank goodness! Can't wait for more exciting news
http://i1265.photobucket.com/albums/jj508/HollyCallum/Mobile%20Uploads/image_zps08afa419.jpg
It's been a while since i've posted but we have BRICKS!!!
AND frames, portaloo and the lock up storage shed!
Woooohooo!! Now we wait for the elusive brickies!! - That will be interesting because our neighbours who were a week ahead of us (we've now caught up) are with HGWA too! I hope we get brickies around the same time
Tonks, our block has some bushland behind it, there is a pond down the end of the street so that has the most bushland I suppose. The estate itself has the John Forrest National park at the boundaries and because we are towards the end, we do get a more natural feel to the area. It's very peaceful in our little spot - very lucky!
If we did build two story we would have had some city views but it wasn't what we wanted at the time. Most of the larger blocks are doing some amazing builds to make the most of their views
http://i1265.photobucket.com/albums/jj508/HollyCallum/063_zpscaf67d42.jpg
Portaloo and Shed
Fingers crossed, not long now!!
Portaloo and Shed
Fingers crossed, not long now!!
The waiting got to me on Monday so we called HG to see what was happening. They said it'll be at least another 2-3 weeks wait. It's pretty disheartening to see everything in place but nothing happening so I haven't visited the block recently. I'm hoping the timeline they've given is fairly accurate - I don't mind waiting as such - it's the not knowing when or if something will happen that I don't like. Anybody else feeling that??
Anyway, just in case I haven't mentioned, we have everything ready to go - bricks, more bricks, sand, frames, portaloo, shed, bin, random long metal pieces... Here's hoping nothing goes walkabout!!
Keep you posted, H x
Quick question i've been meaning to ask all of you...
When our first set of bricks were delivered almost all of our pipes (bathrooms, kitchen etc) were run over and either flattened or broken. Did this happen with anyone else??
ALSO!!
Quick question i've been meaning to ask all of you...
When our first set of bricks were delivered almost all of our pipes (bathrooms, kitchen etc) were run over and either flattened or broken. Did this happen with anyone else??
Quick question i've been meaning to ask all of you...
When our first set of bricks were delivered almost all of our pipes (bathrooms, kitchen etc) were run over and either flattened or broken. Did this happen with anyone else??
Aww I can definitely relate to the torture of waiting for brickies! It seems like its a common thing now to be waiting 1-2months for brickwork to start
And yes our pipes were all mostly damaged as well. Apparently this doesn't really matter as they get cut off at a later stage anyway.
I hope the rain will stop during the day so that the brickies can get a move on to your house!!!
I drove past last week and it looks like the neighbours have started their bricks
They have marked out the walls on the pad and there are pieces of wood etc around the bricks. Kind of sad how excited I was over pieces of wood and the movement of things but I was!
Fingers are crossed that we see some brick laying this week!!!!! It will have been ten weeks if they get them down this week. I think we've waited long enough
We have progress!! After a couple of emails to HG we have FINALLY seen some movement on the block!! Today we drove past and saw that they haved moved the windows to their spots... So naturally I had to take a closer look!
They have marked out the walls on the pad and there are pieces of wood etc around the bricks. Kind of sad how excited I was over pieces of wood and the movement of things but I was!
Fingers are crossed that we see some brick laying this week!!!!! It will have been ten weeks if they get them down this week. I think we've waited long enough
They have marked out the walls on the pad and there are pieces of wood etc around the bricks. Kind of sad how excited I was over pieces of wood and the movement of things but I was!
Fingers are crossed that we see some brick laying this week!!!!! It will have been ten weeks if they get them down this week. I think we've waited long enough
Any updates Holly? I hope they have started on your place now. We waited 9 & a half weeks for brickies
Related
14/05/2024
9
And we're finally moving forward! Trenches and plumbing in, should hopefully see a slab any day now.
12/02/2024
0
hi guys. Please be nice. First time home builder in Qld. I would like some feedback please on whether I should build my granny flat first before my main house at the…