Knockdown/rebuild with Rawson - Metford33
Page 3 of 5
No sign of the brickies today but the chippies were back to finish off the front porch cedar work
The garage is on the left side of the pics, they've only just framed it. No windows in the garage
We also decided to have a site variation for the water tap in the fridge space after using my sisters fridge that had filtered water from a water tap during the Easter weekend, we wanted it in our new house too lol... $380 later though!
We are 1/3 way through bricking, only two brickies on our house so it's taking forever! Should be done by the end of this week with the roof (colourbond) coming the week after...we shall see!
That's great Ezza33 about the bricking. Our bricks were delivered last week too and I thought that was a while off. Rawsons must do things in a different order. We're the only house in the street to not have roofing or guttering yet but already have bricks there
Thanks fizzed! Hopefully the thread isn't a long one
Brickies finally finished on Saturday. What was supposed to take a week, took five even with great weather. Roof was supposed to arrive last week but unless we ordered see through colourbond, I don't think it's there
Our house nearly didn't end up with those brick piers at the bottom of each pillar as it wasn't in our original tender and we didn't think to check that. Luckily was picked up by the colour consultant who added it to a variation
Our roofing is nearly done. Hoping they'll start bricks by end of the week.
Has anyone been given a finish date by any chance? I'm thinking late-July?
We've been told late Sep/early Oct as a guestimate. Lots of demand for not many tradies in Canberra so we are going to have to be patient. So hard when you see it start taking shape in front of you. I want to move in right now! Be a bit wet when it rains, though
Hooray for roof!
Our internal electrical wiring and plumbing is fine, insulation went in yesterday and they should start gyprocking today
We have the majestic too but made a couple of changes to the front porch. I didn't actually notice the number of posts on the design itself, how many have you got?
Hooray for roof!
Our internal electrical wiring and plumbing is fine, insulation went in yesterday and they should start gyprocking today I'm getting impatient and want it done!
Hooray for roof!
Our internal electrical wiring and plumbing is fine, insulation went in yesterday and they should start gyprocking today
Can't wait to see some pics of your gyprock! Super-exciting!
Related
10/01/2024
1
if the original house is in good condition most of what you listed could be added in stages without the need for KDR and costs and disruption of having to live elsewhere…
25/05/2023
0
Hi We have finally decided to complete a KDR on our corner plot in NE Melbourne suburbs. Given its a corner plot approx. 400 sqm just a standard design may not fit the…
18/01/2024
1
multiple occ properties are always billed by trades at a premium, rarely per sqm for the lot. You either have trades you know whoe will do by sqm or youre going to get…