Hey there,
how is your re-bricking coming along? What's the latest with EB ?
Browse Forums Building A New House Re: CALLING JAMIET 2May 15, 2008 9:55 am It's happening. I'm going out on-site on the weekend. I'll probably take some photos as well. Two weeks ago, the bricks were delivered and the drainpipes removed, but I haven't been out since to check the progress.
My site supervisor got a call from my partner yesterday and she was told there's about 2 full weeks of bricking left and mid-June for settlement. I've called the office to ask about penalties and the rental guarantee and they told me they will supply all that information and amounts closer to settlement. They are way over the contract period so we'll see how much their customer committment guarantee that appears in the Sunday papers every week is worth (I also made them add the guarantee to the contract). Re: CALLING JAMIET 3May 15, 2008 3:10 pm Hi jamiet
we recently signed a contract with them & that 'customer guarantee" page was actually bound with the contract. We wanted to have the phrase relating to the $380 rent which appears at the bottom of that sheet (in fine print) , included in the actual contract but decided against it. We thought that if they had the 'customer guarantee' bound with the contract, then that should be sufficient (hoped). Hope we did the right thing. We're also interested in whether that guarantee is worth the paper it's written on Time will tell. Keep us posted with your problems. We are most interested. Built the Eden Brae Cambridge 34 Family with Boston Corner Facade |