Building in Honeywood Estate, Wandi - SLABBED with pics
Page 1 of 2
So the land is 375sqm and settled in September, we just signed off on our final plans and are currently waiting for council building permits and unconditional bank approval, which was approved originally, but when the plans finally went thru to the bank, the approval had expired and now we have to start application again - thanks NAB for that extra stress! So we anticipate slab will be 4-6 weeks away (fingers crossed).
I will add plans when I make a photo bucket account.
Looking forward to sharing this building journey with you all.
TIMELINE:
14/4/13 Land deposit
30/4/13 Pre contract/deposit
18/9/13 Land settlement
23/9/13 Pre start
9/10/13 Final plans
17/10/13 Tap
21/10/13 Council app
29/10/13 Finance app
28/11/13 Site scrap/sand pad
5/12/13 Footings earth works
6/12/13 Footings poured
7/12/13 Concrete pad
Cheers, Met.
Floorplan
Elevations
Electrical
Render to garage & verandah: Shale Grey
Bricks: Alkimos
Render to near front windows: Charcoal
Render to blade wall: Windspray
Front door colour: Dune
Windows: Anodized Silver Grey
Paving to driveway: Granite Storm Cloud with Tundra border
Paving to Alfresco: Charcoal with Grey border
What colour is your kitchen going to be?
Kitchen with new glass splash back
Internal wall and door paint sample
Entrance door and door furniture 1200mm x 28 course in Dune
Ensuite (white tile should be lanka fashion white - same as main bathroom)
Bathroom, Laundry and WC
Carpet, roller blind sample, ensuite floor tile and main floor tile (bathrooms in 300mm and living areas in 450mm)
Yes we are near the Telethon home, we have the same park out the backyard, but about 10 blocks down the hill towards the freeway. Where abouts are you situated?
This looks really close to my block! Girlfriend and I purchased lot 441. Building with Aussie Living, I anticipate that it will start soon.
I have some news! We have a back fence, gate (supplied by the developer) AND a water tap. Plans are still with council, fingers crossed that will be approved soon and we can finally start to build.
Not sure what exact stage we're up to, but I imagine plans are stuck with the council. Hopefully I will get around to making a thread tonight, would love to document everything about building our first house
Now we have to send this letter to bank before they will give us valuation on the house and unconditional approval. I am not sure what the hold up is with NAB, but they are really annoying me now. It's taken nearly 4 weeks for them to get there s#it together. Once house is finished I am swapping all my banking to another company!
http://www.avelinghomes.com.au/building-process-page/ for future reference
joining the honeywood community!