I will update with plans etc when I can but we have Pre-Start on 7th Oct and we're trying to sort out our electrical plan and decide where to plave the LED downlights that come in the package.
To give you an idea of the house size we're building a modified of the Bordeaux Contempo. Living area 240sqm, Alfresco 31.56sqm.
Can people that have built with HomeGroup and used the LED's that come in the package let me know how bright they are and how many they used in the living/dining & kitchen areas.
We have 25 LED's all up throught the house, 1 per room and we were thinking of taking them out of the bedrooms to utilise in the above areas and main entrance hallway. I know they're brighter than the older halogen style but just not sure how many we'll need.
Any help would be much appreciated......Thanks
Our Build Timeline
18/06/2013 - Settled on land
22/07/2013 - HGWA contracts finalised, but have had a few hiccups with finance issues (banks & HGWA's end, not ours) 26/08/2013 - Finance approval. Followed by more red tape issues as we were putting in a sum towards the build costs so there were forms and evidence to provide both to the bank & HGWA..
05/09/2013 - HGWA confirmed that the 'unconditional finance approval' was in place.
07/10/2013 - Prestart.
21/10/2013 - Developer approval of the deisgn
24/10/2013 - Scheduling begins - advised this process takes 4-6 weeks
24/10/2013 - Building permit applied for
31/10/2013 - Building permit granted
17/12/2013 - Scheduling finialised and passed to contruction dept
07/01/2014 - Materials begin to arrive at site
09/01/2014 - Earthworks begin
20/01/2014 - Site plumbing done
21/01/2014 - Slab started
23/01/2014 - Slab finished - told curing time 10-15 days

14/02/2014 - Bricks delivered.
24/02/2014 - Bricklaying started

19/03/2014 - Plate Height reached

27/03/2014 - Roof frame started

16/04/2014 - Roof complete

15/05/2014 - Lock up





23/07/2014 - PCI
24/07/2014 - We got keys